Armow Wind Project Fast Facts

| 180 MW wind energy generation project |
| Power equivalent: approximately 55,000 Ontario homes |
| Estimated $10 million in property taxes generated over 20 year contract period |
| 12 - 18 month construction period |
| Up to 200 jobs during construction period |
| Up to 15 permanent jobs during operations, in addition to local contractors |
| Project area: approximately 46,000 acres |
| Surface area affected during operations: typically less than 1% of total project area |
Project Timeline*
| Commence Environmental Consultant site visits | August 2011 |
|---|---|
| Project Description Report posted to public | November 2011 |
| Notice of Proposal | November 2011 |
| Public information sessions | December 2011 |
| Reports available for public review | September 2012 |
| Public information sessions | November 2012 |
| Submission of REA application | November 2012 |
| Start of construction | 2013 |
| Commercial Operation date | 2014 |
*These initial project timelines may change during the development and construction phases.